Centennial Community Housing Servicing

The Centennial Community Housing Servicing project will design and construct infrastructure services for the future community housing development in the Centennial area. The location of the Centennial area is on the west side of Sherwood Drive, north of Lakeland Drive and south of Highway 16. Servicing will include an industrial collector roadway, water service, sanitary service, storm system and a stormwater management pond.

Map of construction area (183.8 KB)

In summer 2020, Mid-City Construction Management Inc. will be completing final lift of asphalt on the Centennial site. Additional work will include concrete improvements around a bus stop and landscaping maintenance work.

Project timeline

This project is currently in the Construction phase.

TPE_Project_Timeline_Construction.jpg

Timeline:

  • Summer 2020: final lift of asphalt construction
  • Fall 2019: substantial completion of Phase 2 construction services
  • May 2018: start of Phase 2 construction services (roadworks, sanitary and storm servicing)
  • Spring 2018: completion of Phase 1 (grading and water servicing work)
  • August 2017: tender for Phase 1 construction services (grading and  water)
  • June 2017: Stantec Consulting was selected as Consultant; design work began
  • May 2017: Request for Proposal to select a consultant

Project contacts:

Emergency contact:
Evan Dirk
Mid-City Construction Management Inc.
(Prime Contractor)
780-777-8505

Transportation Planning and Engineering
780-464-8279
transportationplanningandengineering@strathcona.ca

County Connect

Ask it, report it or suggest it using County Connect

Related pages

Last updated: Thursday, July 30, 2020
Page ID: 49709