Range Road 232, from Township Road 534 to approximately 450 metres south, is planned to be upgraded to an improved two-lane rural roadway with shoulders.
The upgrades will provide a safe and sustainable roadway to help support the current and future traffic. The upgrades will tie into the existing improved Range Road 232 south.
Proposed upgrades include:
- Widening the current 7 metre roadway to a 10 metre roadway (3.5 metre wide lanes and 1.5 metre wide shoulder)
- Improving the roadway to a hot-mix asphalt surface
- Providing gentler ditch side slopes, where possible
- Improving pedestrian crossings at Township Road 534
Project timeline
This project is complete with deficiencies.Â
Timeline:Â
- April 2020: roadway design
- May to September 2021: Road construction Â
Project contacts:
Transportation Engineering and Operations
Phone: 780-417-7100
Email: transportation@strathcona.ca
Consultant:
Heidi Ehrentraut
Project Manager
Stantec Consulting Ltd.
780-917-7033