Ardrossan Hamlet Roads Upgrade

The purpose of the Ardrossan Hamlet Roads Upgrade project is to enhance road safety, efficiency and usability for residents. Effective and efficient infrastructure contributes to quality of life and place in our community, making Strathcona County one of Canada’s most liveable communities.

The scope of this project includes upgrades to:

  • Point-Aux-Pins Creek Bridge
  • Main Street 

  • Range Road 221A 
  • Third Avenue and Queen Street 

View a map of the concept. (3.1 MB)

 

Project timeline

The planning, design and construction of this multi-phased project is scheduled to take place from fall 2015 into the coming years, pending council approval of annual budgets.

  • 1. Point-Aux-Pins Creek Bridge Project

    Permanent link to Point-Aux-Pins Creek Bridge Project

    With the Main Street loop completed, and further development happening in the Hamlet of Ardrossan, the bridge crossing Point-Aux-Pins Creek needs to be replaced. The narrow bridge is not built to accommodate the increased demands. The scope of this project component consists of upgrading the current Point-Aux-Pins Creek Bridge into a 9.0m two-lane, rural, standard collector road with a 3.0m asphalt trail located on the west side of the new bridge.

    Project timeline

    This project is currently in the Design phase.

    Project Timeline - Design

    Timeline:

    • March 2018 – Design expected to be complete
    • August 2017 – Consultant selected to complete preliminary and detailed design
  • 2. Main Street Project

    Permanent link to Main Street Project

    The scope of this project component is to upgrade Main Street from Range Road 221A to Arbour Close into a two-lane, standard rural collector road. The project will include the construction of approximately 250 meters of sidewalk on the west side of the road. In addition, some minor traffic calming will be introduced at the intersection of Third and First Avenue.

    Project timeline

    This project is currently in the Planning phase. Timeline still to be determined.

    Project Timeline - Planning

  • 3. Range Road 221A Project

    Permanent link to Range Road 221A Project

    The scope of this project component is to upgrade Range Road 221A from Queen Street to King Street into a two lane, rural, standard collector road. The project will include constructing approximately 325 meters of roadway upgrades.

    Project timeline

    This project is currently in the Planning phase. Timeline still to be determined.

    Project Timeline - Planning

  • 4. Third Avenue and Queen Street Project

    Permanent link to Third Avenue and Queen Street Project

    This project is now substantially complete. A small amount of maintenance is scheduled during the next two years and a final acceptance inspection is scheduled in the fall of 2019.

    Project timeline

    This project is currently in the Completed phase.

    Project Timeline - Completed

    Link to completed projects - Ardrossan Third Avenue and Queen Street

 

Additional background:

Further information:

Transportation Planning and Engineering